Technique Data
Test Items | Index | |
Dry | Surface dry | ≤20Minutes |
Time | Hard dry | ≤4hours |
Pencil hardness | 2H | |
Flexibility | ≤0.03mm | |
Bonding strength | ≥60s | |
Adhesion (Grid method) | ≥2 | |
Waterproof | There was no obvious change in 7 days |
Construction Program
Theoretical quantity
| 0.13-0.17kg/㎡ per coat (assuming a dry film of 30 μ m) |
Number of coating layers
| 1 coat of airless spray, 2 coats of roller coating and brush coating (It is recommended to apply 1 coat of epoxy primer first when applying paint to the concrete) |
Recoating interval time
| It is best to have an interval of more than one hour |
Execution conditions
| Before construction, the base layer must be dry, dust-free, flat, free of oil stains and other dirt |
Construction environment
| The construction temperature should be between 5 and 40℃, and the relative humidity should be less than 80%. Construction is not advisable on rainy or snowy days. |